All or nothing nuclear power – from 24/7 to 0/365

The last few months have seen some definite signs that commercial nuclear power is not the wave of the future but a way of boiling water that might be seen as a twentieth century folly. Four commercial nuclear reactors have been shut permanently ostensibly for different reasons, but economics underlies them all.

Crystal River in Florida came first, in early February 2013. It had been shut since 2009. Like many other pressurized water reactors, it had to have a premature replacement of its steam generators, the huge heat exchangers were the hot reactor water (“primary water”) heats up water in the secondary circuit to make the steam the drives the turbine-generator set. The outer layer of the containment structure cracked during the replacement. Duke Energy, the owner, determined it was too costly to fix the problem. See Duke’s press release at http://www.duke-energy.com/news/releases/2013020501.asp

The 556-megawatt Kewaunee reactor in Wisconsin came next, in early May, unable to compete with cheap natural gas and falling electricity prices. Indeed, electricity consumption in the United States is declining even as the economy recovers from the Great Recession due in part to the increasing efficiency of electricity use. There doesn’t appear to be enough money in the reserve fund for decommissioning at present – see the New York Times article at http://www.nytimes.com/2013/05/08/business/energy-environment/kewaunee-nuclear-power-plant-shuts-down.html.

San Onofre, with two reactors, came next. Both had been down since early 2012, when excessive wear of steam generator tubes and leaks of primary water were discovered. The steam generators were new, but contrary to the company’s claims, it turned out that the new ones were not copies of the original licensed design. A long, contentious process followed; prospects for a green light to restart faded. The blame game between the supplier of the steam generators, Mitsubishi, and the majority owner, Southern California Edison grew intense (and it continues). Announcing the decision to close the plant, the SCE President Ron Litzinger said: “Looking ahead, we think that our decision to retire the units will eliminate uncertainty and facilitate orderly planning for California’s energy future.” (See the La Times article at http://www.latimes.com/local/lanow/la-me-ln-edison-closing-san-onofre-nuclear-plant-20130607,0,7920425.story).

Nuclear plants were supposed to create certainty, reliability, predictability, 24/7 operation. But in the last few years, this has given way to a new reality. Nuclear reactors are 24/7 until they become 0/365 with little or no notice. The above are just four examples. Before the Fukushima disaster, Japan had 54 reactors. Four were irretrievably damaged by the accident. In the 15 months that followed, the other 50 were progressively shut or remained in shut down mode. In the last year, only two have been restarted. It will be a contentious process before any more of them can be restarted. It is possible none will be. Many in Japan assume they won’t be for they are installing solar power at rapid rates – 1.5 gigawatts in the first quarter of 2013 alone – equal to about one-and-a-half reactors in peak power output. About 6 gigawatts would be required to generate an equal amount of electricity to one typical power reactor. Capacity comparable to that will likely be installed in Japan this year.

Finally, Germany prematurely shut eight reactors following Fukushima, consolidating and accelerating the post-Chernobyl process of phasing out nuclear power altogether (the end date is now set for 2022).

But officialdom in the United States still clings to the idea that we need nuclear power. So reliable, so baseload, so twentieth century (oops, wrong century).

Fukushima reflections on the second anniversary of the accident

Statement of Arjun Makhijani for the March 2013 conference commemorating the Fukushima accident
To be read by Helen Caldicott

I appreciate that my friend, Helen Caldicott, one of the two people who inspired my book Carbon-Free and Nuclear-Free (the other was S. David Freeman) has agreed to read a brief statement from me on this second anniversary of the Fukushima disaster. I wanted to share two of the new things I have learned as I have followed the consequences of Fukushima unfold.

First, the Japanese government proposed to allow doses as high as 2 rem (20 millisieverts) per year to school children, claiming that the risk was low or at least tolerable. An exposure at this level over five years – 10 rem in all — to a girl, starting at age five, would create a cancer incidence risk of about 3 percent, using the [age- and gender-specific] risk estimates in the National Academies BEIR VII report.

Now imagine that you are a parent in Japan trying to decide whether to send your daughter to such a school. Roughly thirty of every hundred girls would eventually develop cancer at some point in their lives; just one of those would be attributable to Fukushima school exposure, according to the risk numbers. But no one would know if their daughter’s cancer was attributable to the exposure at school and neither would the Japanese government’s radiation bureaucrats. Why is it difficult to understand that while the risk attributable to school contamination would be one in thirty, the proportion of parents stricken with guilt and doubt would be closer to one in three? Would you ever forgive yourself if you made the decision to send your daughter to that school? Or your son, though the risk attributable to Fukushima exposure would be less than that experienced by girls?

Indeed, due to the long latency period of most cancers, you would be fearful even if no cancer had as yet appeared. The Pentagon understood this when a Joint Chiefs of Staff Task Force evaluated the extensive contamination produced by the July 1946 underwater nuclear bomb test (Test Baker) at Bikini for its usefulness in war. Here is a quote from their 1947 report:

“Of the survivors in the contaminated areas , some would be doomed by radiation sickness in hours some in days, some in years. But, these areas, irregular in size and shape, as wind and topography might form them, would have no visible boundaries. No survivor could be certain he was not among the doomed, and so added to every terror of the moment, thousands would be stricken with a fear of death and the uncertainty of the time of its arrival.”

Compare this for yourself with the aftermath of Fukushima and the plight of the parents.

Second, nuclear power’s conceit was that nuclear power is 24/7 electricity supply. Since Fukushima, over sixty of the world’s light water power reactors have been prematurely shut for a variety of reasons, though just four reactors were stricken by the accident: 52 in Japan, eight in Germany, several in the U.S. Even if some are eventually restarted, nuclear power has shown a unique ability to go from 24/7 power supply to 0/365 essentially overnight for long periods– hardly a convincing claim of reliability.

We can do better than making plutonium just to boil water or polluting the Earth with fossil fuel use. When I finished Carbon-Free Nuclear-Free in 2007, I estimated it would take about forty years to get to an affordable, fully renewable energy system in the United States. Today, I think in can be done in twenty-five to thirty years. Are we up to the challenge? Finally, I truly regret I cannot be there to publicly thank and honor my friend Helen for inspiring Carbon-Free, Nuclear-Free, which you can download free from ieer.org, also thanks to her. I wish you a very productive conference.

(Also see IEER’s publication Plutonium: Deadly Gold of the Nuclear Age, June 1992.)

When small is not beautiful is it at least cheap?

On February 6, 2013, Dan Stout, who is the Tennessee Valley Authority’s senior manager for its Small Modular Reactor project, gave a colloquium at the University of Tennessee in Knoxville. Much of the talk was just nuclear-boosterism. For instance, he claimed that “nuclear power was tested hard in 2011. It remains safe reliable and affordable.”

There was no mention of the fact that post-Fukushima, about 60 of the world’s light water reactors were closed for one reason or another, mainly in Japan and Germany, taking them from 24/7 power generation to 0/365. He said nothing of the enormous social, economic, and environmental dislocation and loss that has afflicted the Fukushima region and beyond since that time. And there was nothing of the Nuclear Regulatory Commission’s Task Force report of July 2011 that found US regulations seriously lacking in a number of respects (http://pbadupws.nrc.gov/docs/ML1118/ML111861807.pdf). But there was some refreshing candor about Small Modular Reactors (SMRs) mixed with this sales talk. His talk is archived at http://160.36.161.128/UTK/Viewer/?peid=fa73ded60b7b46698e9adc0732101a76

SMRs are supposed to overcome the loss of economies of scale by using assembly mass-manufacturing techniques such as are used for cars and passenger aircraft. The site set up would be standardized and the set up and commissioning on site would be relatively quick (36 months). So “economics of replication” would replace the “economies of scale” (one of the principal reasons that reactors got larger as time went on).

But there is a chicken and egg problem here, to quote a cliché. You’ve got to have a lot of orders before you can set up your assembly line and produce cheap reactors, but you have to have demonstrated your reactors are certified before you get the nuclear masses lining up to order them, given the risks involved. There are no such orders yet; no assembly line is in sight.

So for now, SMRs would be “cobbled together” in existing facilities. “Does the federal government want to help?” he asked rhetorically. “I don’t know,” he went on. “We’re going to find out. I am not going to make your electric bills all triple because of this project. That’s just …TVA won’t do that.” (Italics added.)

So for the foreseeable future without massive subsidies, nuclear power using SMRs will be the same as nuclear power with the present Atomic Leviathans – expensive and in need of government subsidies. But you have to hand it to Mr. Stout for one thing. Unlike Georgia Power and South Carolina Electric and Gas, two utilities building the new large behemoth variety (the AP1000), he is not willing to saddle TVA ratepayers with the cost of yet another nuclear gamble. TVA has been there and done that, and is still doing it with large reactors. A large part of TVA’s indebtedness is from 1970s and early 1980s was due to the cancellation mid-stream of costly and unneeded reactors. No, prudently for TVA, Mr. Stout wants the taxpayers to take the deal.

And the federal government has obliged by committing up to half of the $452 million proposed for SMRs to Babcock & Wilcox, designer of the mPower, 180 megawatt reactor, and the TVA to advance design and certification. [1] B&W had spent over $200 million on the project as of the middle of last year. Where will it lead other than the “cobbled together” machine? Specifically, what will it take to get an assembly line? Here is how Mr. Stout explained it:

So the concept is that you gotta to have an assembly line cranking out repeatable parts, achieving a standardized vision of lots of mPower reactors. That creates the nth of a kind plant that has the efficiency in cost. I’m building Unit One. I don’t want to pay for B&W’s factory with automation to crank out repeatable parts. So that creates a contracting challenge… So as you scratch your head and puzzle how does work, remember the math won’t work on one unit. In fact our unit is most likely going to be, I’m going to use the word “cobbled together”, it’s going to be manufactured within existing facilities. But if B&W can get an order backlog of a hundred SMRs and they are going to start delivering them in China and India etc. then they’ll be able to go get the financing and build the building and have new stuff put in place to crank out these parts in a more automated manner. So as long as the design is the same this should all work. The devil is going to be in the details and in the oversight and in the inspections. [italics added]

A hundred reactors, each costing almost $450 million, would amount to an order book of $45 billion. That does not include construction costs, which would double the figure to $90 billion, leaving aside for now the industry’s record of huge cost escalations (see B&W 2012 presentation at http://www.efcog.org/library/council_meeting/12SAECMtg/presentations/GS_Meeting/Day-1/B&W%20mPower%20Overview%20-%20EFCOG%202012-Ferrara.pdf for total estimated cost figure of $5000 per kW). This would make the SMR launch something like creating a new commercial airliner, say like Dreamliner or the Airbus 350. There were a total of 350 orders for the A350 in 2007, when it was seriously launched as a rival to Boeing’s Dreamliner. The list price of the A350 is between about $250 million and $400 million (rounded — http://www.airbus.com/presscentre/corporate-information/key-documents/?eID=dam_frontend_push&docID=14849), which would make the initial order total the same order of magnitude in cost as 100 completed mPower SMRs.

The end of this decade is the target for the commissioning of the first mPower reactor (the most advanced SMR in planning and design and the only one with substantial federal government support so far). It would take some years after that – well into the 2020s – to fully prove the design and, if needed, debug it. It stretches credulity that China and India, which along with Russia, are the main centers of nuclear power construction today, would put in orders totaling a hundred reactors much before 2020. Indeed, if they were that attracted to SMRs, why would they not pay the license fees and set up the assembly line themselves? Most notably, China, where 28 reactors are under construction (http://www.world-nuclear.org/info/inf63.html), already has a much better supply chain than the United States. So the government subsidy to B&W and TVA would likely pave the way for an assembly line in China! Unless…

The federal government orders a hundred reactors or entices utilities to do so with massive subsidies. We are talking putting tens of billions of taxpayer dollars at risk – at a time when the air is full of talk of furloughs for teachers, air traffic controllers and civilian Pentagon employees, among others, and cutbacks in training of military personnel.

What happens if a common design or manufacturing problem is discovered as it was with the Dreamliner batteries? How is a mass manufacturer of reactors, whose internals become radioactive after commissioning, going to recall them or their major components? No word from Mr. Stout, or that I am aware, from any of the SMR enthusiasts, about this. For safety issues see the testimony of Dr. Ed Lyman of the Union of Concerned Scientists, at http://www.ucsusa.org/assets/documents/nuclear_power/lyman-appropriations-subcom-7-14-11.pdf.

IEER and Physicians for Social Responsibility wrote an SMR fact sheet in 2010, outlining such concerns. (http://ieer.org/resource/factsheets/small-modular-reactors-solution/) They have only deepened with time. SMRs are highly unlikely to provide the industry the nuclear renaissance that has so far eluded it. Indeed, by the time the first ones are being commissioned, solar photovoltaics, smart grids, and a host of other disturbed electricity technologies will be more economical. Wind-generated electricity already is. No one has a perfect crystal ball in the energy business, but mine tells me that SMRs will not solve our CO2 woes. They are likely to be economically obsolete before this decade is done – and the end of this decade is the target date for the first mPower reactor to come on line. So why go there, to a time when there are going to be only costs and little prospect of benefits?

Notes:

  1. This sentence was corrected on April 3, 2013. The original text “And the federal government has obliged by committing $452 million to Babcock & Wilcox, designer of the mPower, 180 megawatt reactor, and the TVA to advance design and certification.” is incorrect. ↩ Return

Is there a role for small modular reactors?

On November 20, President Obama announced funding to develop small modular reactors. The US went from small reactors to large ones to get economies of scale. Power reactor generating capacity goes up faster than material costs — one of the sources of economies of scale. Despite that, large reactors are very expensive and the so-called nuclear renaissance is sputtering. So now the new nuclear nirvana is going back to small reactors. It is unlikely to work. Government should not still be subsidizing nuclear 55 years after the first “commercial” nuclear power plant came on line in 1957. Like the first time, government is rushing in without due consideration of many of the problems.

For more information on SMRs and their potential problems, see the IEER-PSR factsheet.

— Arjun